Monthly Archives: April 2012
Today is the first day…
…of the rest of your life, Geritol. Use only as directed. Welcome back to the DOG progress report. Editorial on the first and second act is (dare I say it?) done. There are some weld edits which require a deeper … Continue reading
Progress on Gerry’s cabin
Gerry’s cabin or Act 2 is very close to it’s final iteration. The length was cut from 9:00 minutes to 8:15, 45 seconds. We lost some lag and tuned the performance by splitting several two shots. My first foray into … Continue reading
Gender based test screening
It occurs that separate test screenings for men and women would be good. I am especially interested in what women think about the Christina character, if they relate to her as a more elegant cut emerges. Is she despised by … Continue reading
Interns and the last test of Version 1.0 2012
Trickster Pictures has two interns through the TBAISD Career-Tech Center’s Film and New Media Program – Cameron and Micah. They’ve been learning how to rotoscope using both After Effects and Mocha and will hopefully be able to contribute to DOG’s … Continue reading
Go Go Go Again
Budgeting for the completion of DOG distills down to a simple formula… Tasks / Team = Duration Each task describes a specific change to some shot, a shot defined as the IN point to OUT point of any edit. A … Continue reading
Roto ramping up
April 2, 2012 I’ve identified the Essential tasks and have assembled a core roto team – this week is the shakedown cruise. I’ve got two interns and two contractors and am interested to see how much progress we make this … Continue reading
Artist reference version 1.1
Introduction DOG was originally shot in 2006 and was revived in the summer of 2011. The objective is to have a festival launch by summer of 2012. If you’re inclined to read this blog, you’ll notice that I have an … Continue reading